At 3 Pillar Homes, we believe the more informed you are about the construction of your new home, the more enjoyable the process will be for you and your family. Therefore, the following provides a detailed description of the sequence of events involved throughout the building process.
We hope that you find this a helpful guide as you follow along throughout the stages involved in the building of your new home.
Client |
3 Pillar |
|
Purchase AgreementOffice Approval & Copy of Contract to Sales/ Client/Realtor/Lender& key info to main vendors for selection process to begin |
||
Color/ Selection Process |
||
Pre Color SelectionSales & Client |
Start Custom Home DesignOrder plot plan |
|
Exterior ColorsMichael David & Client |
||
CabinetsScioto Kitchens & Client |
Office Checks & BalancesGather Info from Vendors Produces Change Order Requests & Submit change order to clients |
|
AppliancesHH Gregg/FineLines & Client |
Client Review & Sign Off of selected items on Change Order |
|
Interior DesignMichael David & Client |
Office EditsColor Selection Sheet and distributes updated costs to client/sales/realtors/lender |
|
Plumbing Fixtures & AccessoriesEastway Supplies |
Adjust Custom Blueprints per change order Plan Review and comments Submit for Permits provide copy to clients |
|
Garage Doors Openers/ FireplacesHamilton Parker |
Pre-Builder Buyer ConferenceReview Package with Super and Full Audit of Job to Date Identify open items & work toward closure/ final selections |
|
Builder Buyer Conferencewith Revisions and Notes |
||
Distribute Start Package to Vendors
|
||
BreakgroundFoundation - activity includes Lot excavation, footers, foundation walls, waterproofing & backfill |
||
Frame CompleteRough framing, roofing, windows, exterior doors & stairs |
||
Rough Mechanicals Start(HVAC, plumbing, electrical, low voltage) |
||
Electrical WalkthroughAt rough electrical star t, there is a client walkthrough with electrician and superintendent to locate options selected |
Office Checks & BalancesGenerates Change Order Request for any additions |
|
Low Voltage WalkthroughAt low voltage star t, there is a client walkthrough with vendor to locate options selected |
Client Sign Off on Change Orders |
|
Light Fixture SelectionsCapital Lighting |
||
Moellering IndustriesReview cabinet layouts with vendor, consider edging styles & other options. Your undermount sink |
Insulation Complete |
|
Landscape, Hardscape, IrrigationBlendon Gardens |
||
Pre-Drywall WalkthroughCheck off all locations & options to date |
||
Drywall / Exterior & Interior Finishes |
||
Pre-Closing WalkthroughHome is substantionally completed |
||
Final Punch |
||
Closing Walkthrough |
||